The example: a site in Batea (Tarragona, Spain). The nearest substation, Ribarroja, is 20.8 km away but has only 2.7 MW available. The first one with room for 5 MW, Aubals (15.0 MW), is 28.3 km away. A 66 kV underground line to it comes to about €10.98M CAPEX and €0.16M OPEX per year: roughly €2.2M per MW for the connection alone.
The example: a site in Batea (Tarragona, Spain). The nearest substation, Ribarroja, is 20.8 km away but has only 2.7 MW available. The first one with room for 5 MW, Aubals (15.0 MW), is 28.3 km away.
A 66 kV underground line to it comes to about €10.98M CAPEX and €0.16M OPEX per year: roughly €2.2M per MW for the connection alone.
What the grid module does:
A 66 kV underground line to it comes to about €10.98M CAPEX and €0.16M OPEX per year: roughly €2.2M per MW for the connection alone.
What the grid module does:
- Available access capacity per substation, updated monthly.
- Capacity forecast (in testing): nodes where capacity may be released because the projects connected to them were rejected, expired or withdrawn. Data from Vigía, our daily tracker of the BOE and Spain's regional gazettes.
- Overhead or underground line routing to the selected substation.
- Preliminary CAPEX and OPEX using references based on ACER's Unit Investment Cost (UIC) indicators, 2023 report.