€10.98M to connect 5 MW: the grid cost to know before you sign the land

The example: a site in Batea (Tarragona, Spain). The nearest substation, Ribarroja, is 20.8 km away but has only 2.7 MW available. The first one with room for 5 MW, Aubals (15.0 MW), is 28.3 km away. A 66 kV underground line to it comes to about €10.98M CAPEX and €0.16M OPEX per year: roughly €2.2M per MW for the connection alone.
The example: a site in Batea (Tarragona, Spain). The nearest substation, Ribarroja, is 20.8 km away but has only 2.7 MW available. The first one with room for 5 MW, Aubals (15.0 MW), is 28.3 km away.
A 66 kV underground line to it comes to about €10.98M CAPEX and €0.16M OPEX per year: roughly €2.2M per MW for the connection alone.
What the grid module does:
  1. Available access capacity per substation, updated monthly.
  2. Capacity forecast (in testing): nodes where capacity may be released because the projects connected to them were rejected, expired or withdrawn. Data from Vigía, our daily tracker of the BOE and Spain's regional gazettes.
  3. Overhead or underground line routing to the selected substation.
  4. Preliminary CAPEX and OPEX using references based on ACER's Unit Investment Cost (UIC) indicators, 2023 report.
It is an estimate for comparing and screening sites before negotiating the land; it does not replace a grid access and connection study. Request a demo: https://terraeolica.com/windsense